News
      Brief Introduction
      Benefits and Scale
      Technology Achievement
      River Close-off and Cofferdam          in Deep Water
     River Close-off and Concrete           Cut-off Wall Construction
     River Close-off on the Divers-           ion Channel
      Concrete Placement
     Fast Concrete Placement
     Phase-III RCC Concrete           Placement
      High Slopes
     Construction of Ship lock
     Metal Structures of Ship lock
      Generating Units
     Environment  Protection
      History
      Owner of TGP
      FAQ
      Exhibition Hall
      Gallery

Phase-III RCC Concrete Placement

Basic facts of the RCC cofferdam are shown as follows: concrete gravity dam, dam crest length of 580 m, dam crest elevation of 140 m, maximum dam height of 115 m, and concrete placement of 1.68¡Á10 6 m3 . The cofferdam was built in two stages. In the second stage, the dam section of 380 m long, 90 m high, concrete placement of 1.1¡Á10 6 m3 was completed within five months, which was surely a incredible achievement in high intensity, great difficulty, tight schedule, and strict quality control.

In order to conquer the above challenges, CTGPC organized relevant institutes and contractors to carry out technological research in advance. Scientific management and new technology approaches helped to finish the task ahead of schedule and create records in RCC concrete placement as follows: maximum placement area of 19,012 m2 , maximum monthly concrete placement of 476000 m3 , maximum daily concrete placement of 21,066 m3 .