News
  Brief Introduction to TGP
  Benefits and Scale of TGP
  Significant Technology Achievement in the      TGP Construction
  River Close-off and Cofferdam in Deep       Water
River Close-off and Concrete Cut-off Wall       Construction
River Close-off on the Diversion Channel
  Concrete Placement on the TGP Dam
Fast Concrete Placement Technology
Phase-III RCC Concrete Placement
  High Slopes outside the Three Gorges Ship      lock and Metal Structures
Construction of High Side Slope of Three       Gorges Ship lock
Metal Structures of Ship lock
  The Design, Manufacture and Installation of      the Units
  Three Gorges Project and Environmental      Protection
  History of Three Gorges Project
  Owner of Three Gorges Project
  Frequently Asked Questions & Answers
  Exibition Hall
  Pictures Collection

Phase-III RCC Concrete Placement

Basic facts of the RCC cofferdam are shown as follows: concrete gravity dam, dam crest length of 580 m, dam crest elevation of 140 m, maximum dam height of 115 m, and concrete placement of 1.68กม10 6 m3 . The cofferdam was built in two stages. In the second stage, the dam section of 380 m long, 90 m high, concrete placement of 1.1กม10 6 m3 was completed within five months, which was surely a incredible achievement in high intensity, great difficulty, tight schedule, and strict quality control.

In order to conquer the above challenges, CTGPC organized relevant institutes and contractors to carry out technological research in advance. Scientific management and new technology approaches helped to finish the task ahead of schedule and create records in RCC concrete placement as follows: maximum placement area of 19,012 m2 , maximum monthly concrete placement of 476000 m3 , maximum daily concrete placement of 21,066 m3 .